Construction Works

  • Utilities relocation works (sanitary sewer and watermain) are underway on Park Hill Road and Eglinton Avenue West.
  • Underway since early spring, the invert tunnel concrete pour continues on both the east and west sides of Allen Road.
  • Shoring and construction for the north east entrance to start as early as June.
  • Shoring on the south side of Eglinton Avenue, at Everden Road, to start as early as late June.
Photo: Concrete being laid to form the foundation for the track
About Alwin 15243 Articles
Alwin Marshall-Squire is the Editor-in-Chief of S-Q Publications Inc., publisher of GTA Weekly News. He oversees all editorial content and leads the publication’s mission to deliver bold, original journalism focused on the people and communities of the Greater Toronto Area. He can be reached at alwin.squire@gtaweekly.ca.