Construction Works at Kennedy Station and At-Grade Eastern Alignment (Ionview, Birchmount, Golden Mile, Hakimi-Lebovic, Pharmacy, O’Connor, and Sloane Stops)
Preparatory works continue in the vicinity of Kennedy Station and along Eglinton Avenue East. Here is an overview of current and upcoming works:
Crews continue to carry out ongoing Preparatory Works and Street Furniture Removal along Eglinton Avenue East between Brentcliffe Road and Midland Avenue. This includes another round of Geotechnical Work in the properties around the existing TTC Kennedy Station.
Crews are mobilizing the Victoria Park – Eglinton Parkette for a clean soil storage site, which means that some trees need to be removed to make space.
Starting on May 1, 2017, there will be a Reduction of Parking Spaces in existing Kennedy Station parking lots.
Recap: Surface Section and Kennedy Station Public Open House On April 5, the Surface Section and Kennedy Station Public Open House was held at St. Maria Goretti Catholic School to share information about the construction of the surface section and the future Kennedy Station Open House. If you didn’t have a chance to stop by, you can see the presentation on our website.
Metrolinx Community Charter Metrolinx is developing a Community Charter to give meaningful and measureable form to our commitment to our residents and communities. In this second phase of the public consultation, we’re seeking your comments on the six promises Metrolinx will make in the Community Charter.
We want to hear from you Please, join us and help shape the Community Charter by submitting your comments online at MetrolinxEngage.com.
Our work and our plan is for this region. But the results are for you. Thank you for taking the time to play a part.
Draft Community Charter Promises
Metrolinx promises to ensure your safety.
Metrolinx promises to invest public funds responsibly.
Metrolinx promises to be considerate and treat you with respect.
Metrolinx promises to seek your input to help us make the best decisions.
Metrolinx promises to keep you informed.
Metrolinx promises to build and operate transit that connects our communities today and tomorrow.
Thank you for your patience as we work to build this important project. Please support your local businesses during construction.
Electrification Will Support Faster and More Frequent Service for Commuters and Families Ontario is transforming how people get around in the Greater Toronto and Hamilton Area and taking a major step forward to electrify the […]
What Work is Taking Place?Crews will be conducting ongoing preparatory work that requires short-term temporary work zones along Eglinton Avenue East between Leslie Street and Midland Avenue. Geotechnical Work Drilling of boreholes to determine the existing […]
What Work is Taking Place? To prepare for the construction of Mount Pleasant Station, crews will relocate and upgrade existing overhead hydro utilities in the vicinity of Mount Pleasant Road and Eglinton Avenue East for […]