Mount Pleasant Station
Eglinton Crosstown

Eglinton Crosstown: Mount Pleasant Station

March 27, 2017 GTA Weekly 0

Construction Works at Mount Pleasant StationMain Entrance support of excavation, also known as shoring, has begun. The work will be contained in the existing site set up and will last for approximately eight weeks. Secondary Entrance […]

crosstown metro linx map for open house
Eglinton Crosstown

Eglinton Crosstown: Sloane Avenue to Kennedy Road

March 20, 2017 GTA Weekly 0

Construction Works at Kennedy Station and At-Grade Eastern Alignment(Ionview, Birchmount, Golden Mile, Hakimi-Lebovic, Pharmacy, O’Connor, and Sloane Stops)Preparatory works continue in the vicinity of Kennedy Station and along Eglinton Avenue East. Here is an overview […]

metrolinx road safety
Eglinton Crosstown

Construction Works at Laird Station

March 17, 2017 GTA Weekly 0

Completion of hydro utilities work continues to support the construction of the future Laird Station, working in the westbound curbside lane on Eglinton Avenue East, from Brentcliffe Drive to Laird Drive. Crews are also completing […]

Computer drawing off what Laird Station will look like after construction
Eglinton Crosstown

Tracking the Eglinton LRT: Laird Station

February 17, 2017 GTA Weekly 0

Crews will be installing and taking readings of above ground and in-ground monitoring points periodically for duration of the project in the vicinity of Eglinton Avenue East and Laird Drive. Short term lane closures on […]