Construction Works at Science Centre Station and At-Grade Western Alignment (Sunnybrook Park, Aga Khan Park & Museum, and Wynford Stops)
Work progresses for station construction and below is an overview of current and upcoming works:
Continued Works at Don Mills Spring-Summer 2017: Support of excavation and utility relocations continue. During this work, a minimum of two thru lanes of traffic in each direction will be maintained during peak hours. Additional lane reductions can be expected on Eglinton Avenue and/or Don Mills Road during off peak hours for additional related works.
Hydro Ductbank Connections Continues: Hydro infrastructure work is ongoing at the Don Mills Road and Eglinton Avenue East intersection. Lane reductions continue intermittently and between 9:00 a.m. and 4:00 p.m.
We held an Open House meeting for Science Centre Station last week on June 15, 2017. If you didn’t have the chance to stop by and learn more about the station and upcoming work, you can check out the presentation online.
Construction Works at Science Centre Station and At-Grade Western Alignment (Sunnybrook Park, Aga Khan Park & Museum, and Wynford Stops)Earlier this month, crews finished driving piles on the southeast side of Eglinton Avenue East and […]
Updated Set Up for Support of Excavation at Mount Pleasant Station Main Entrance What Work is Taking Place? Since February 2017, crews have been conducting support of excavation work, also known as shoring, at the Main […]
Construction Works at Science Centre Station and At-Grade Western Alignment (Sunnybrook Park, Aga Khan Park & Museum, and Wynford Stops) Crews to continue utility relocations at the northwest and southwest corners while road widening work […]
Leave a Reply