Construction Works at Science Centre Station and At-Grade Western Alignment (Sunnybrook Park, Aga Khan Park & Museum, and Wynford Stops)
Work progresses for station construction and below is an overview of current and upcoming works:
Continued Works at Don Mills Spring-Summer 2017: Support of excavation and utility relocations continue. During this work, a minimum of two thru lanes of traffic in each direction will be maintained during peak hours. Additional lane reductions can be expected on Eglinton Avenue and/or Don Mills Road during off peak hours for additional related works.
Hydro Ductbank Connections Continues: Hydro infrastructure work is ongoing at the Don Mills Road and Eglinton Avenue East intersection. Lane reductions continue intermittently and between 9:00 a.m. and 4:00 p.m.
We held an Open House meeting for Science Centre Station last week on June 15, 2017. If you didn’t have the chance to stop by and learn more about the station and upcoming work, you can check out the presentation online.
Alwin Marshall-Squire is the Editor-in-Chief of S-Q Publications Inc., overseeing editorial strategy for GTA Weekly, GTA Today, and Vision Newspaper. He leads the publications’ mission to deliver bold, original journalism focused on the people and communities of the Greater Toronto Area, Canada, and the global Caribbean diaspora.
Also writes for GTA Weekly and GTA Today.
The Eglinton Crosstown includes a 10-kilometre underground portion, between Weston Road and Laird Drive, where 15 below-grade stations are under construction. Eleven will be built using a “cut-and cover” method and four, including Laird Station, […]
What Work is Taking Place?Crews will be conducting ongoing preparatory work that requires short-term temporary work zones along Eglinton Avenue East between Leslie Street and Midland Avenue. Geotechnical Work Drilling of boreholes to determine the existing […]
Construction Works at Kennedy Station and Eastern Surface Section(Ionview, Birchmount, Golden Mile, Hakimi-Lebovic, Pharmacy, O’Connor, and Sloane Stops)Preparatory works continue in the vicinity of Kennedy Station and along Eglinton Avenue East. Here is an overview […]