Eglinton Crosstown: Mount Pleasant Station Construction

Eglinton crosstown

Construction Works at Mount Pleasant Station

  • This week and next, crews are working to reconfigure the traffic signals at the intersection to hang the lights on cables instead of poles.
  • Main Entrance Support of Excavation (shoring) continues. This week and next, crews are adjusting the work zone to occupy an additional lane on Eglinton Avenue East to allow for space for piles to be installed along the south perimeter of the future station entrance.
  • Secondary Entrance Support of Excavation (shoring) is still on hold as crews work to relocate an sanitary sewer within the site.

Recap: Mount Pleasant Station Open House
We held an Open House meeting for Mount Pleasant Station on April 11, 2017. If you didn’t have the chance to stop by and learn more about the station and upcoming work, you can check out the presentation online.

Thank you for your patience as we work to build this important project.
Please support your local businesses during construction.


For more information about Mount Pleasant Station, please contact:
Brittany Maxwell
East Community Office
660 Eglinton Avenue East (Sunnybrook Plaza)
416-482-7411

Be the first to comment

Leave a Reply

Your email address will not be published.


*