Eglinton Crosstown: Shoring and Utility Work in the Roadway at Mount Pleasant Station

Eglinton crosstown mount pleasant stage 1 construction

What Work is Taking Place?

As early as June 2017, crews will begin shoring of the station box in the roadway, starting on the north side of Eglinton Avenue East.

Shoring is a common step in the process of constructing the foundation of a building.  Steel piles, as well as braces and tie-backs, will be installed around the perimeter of the station box to support excavation.

Shoring in the roadway will be completed in four stages.  Stages 1 and 2 will take approximately two and a half (2.5) months to complete. 

Crews have already started support of excavation work (shoring) at the Main and Secondary Entrance sites and that work will continue as shoring works move into the roadway.  The entire shoring process for future Mount Pleasant Station will take approximately 12.5 months to complete.

Crews will also complete utility relocation while they are occupying the roadway for shoring works.

Timing

  • Work will begin as early as May 2017.
  • Work may occur between 7:00 a.m. and 11:00 p.m. seven days a week.
  • The contractor may not always work during the permitted hours, but may do so at its discretion.
  • Work may be rescheduled due to weather conditions or unforeseen circumstances.
  • In the event that overnight work is required, Metrolinx and CTS will notify the public in advance and monitor activities throughout.

Be the first to comment

Leave a Reply

Your email address will not be published.


*