Shoring and utilities relocation works continue. For the remainder of summer, the following is scheduled:
• Continue piling at the southeast side of the station box • Continue roof slab construction at the southwest side of the station box • Drill move from Secondary to Main Entrance • Commence piling at the Main Entrance
Complete: Shallow excavation at the southwest side of the station box.
Underway: Guidewall construction at the main entrance (northeast corner, Dufferin & Eglinton).
Drill Move
The relocation of the drill rig from the Secondary Entrance to the Main Entrance will take place soon. The drill rig will be used to commence piling at the Main Entrance.
• Week of August 7 • Starting at 10:00 p.m. for approximately 15 minutes • Traffic will be stopped in all directions during the operation
Alwin Marshall-Squire is the Editor-in-Chief of S-Q Publications Inc., publisher of GTA Weekly News. He oversees all editorial content and leads the publication’s mission to deliver bold, original journalism focused on the people and communities of the Greater Toronto Area. He can be reached at alwin.squire@gtaweekly.ca.