What Work is Taking Place?
Starting as early as May 2017, crews will start support of excavation work, also known as shoring for the Brentcliffe Portal. Steel piles, as well as braces and tie-backs will be installed around the perimeter of the portal entrances to support excavation. Shoring will be conducted in phases, within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. The first phase will take approximately twelve (12) weeks to complete. The entire shoring process will take approximately twenty-four (24) months to complete. Timing