Toronto City Council approves the cycling network plan and extends two temporary ActiveTO Cycling Network Expansion projects

ActiveTO Cycling Network

Today, Toronto City Council approved the Cycling Network Plan: 2022 Cycling Infrastructure Installation – First Quarter and 2021 ActiveTO Cycling Network Expansion Project Updates report, which will add 10 kilometres of new bikeways, improvements on five kilometres of existing bikeways, and extend two temporary ActiveTO Cycling Network Expansion projects.

The changes will improve safety and mobility options by providing improved cycling connections to transit, parks, local schools, businesses and residences.

The projects are planned for installation from 2022 to 2024, and include the following:
•       Bartlett-Havelock-Gladstone Cycling Connections: www.toronto.ca/community-people/get-involved/public-consultations/infrastructure-projects/bartlett-havelock-gladstone-cycling-connections/
•       College Street Upgrades: www.toronto.ca/community-people/get-involved/public-consultations/infrastructure-projects/college-street-upgrades/
•       Douro-Wellington Cycling Connections: www.toronto.ca/community-people/get-involved/public-consultations/infrastructure-projects/douro-st-wellington-st-bike-lanes/
•       Knox Avenue Cycling Connections: www.toronto.ca/community-people/get-involved/public-consultations/infrastructure-projects/improvements-to-woodfield-road-monarch-park-avenue-knox-avenue/knox-avenue-bikeway-connection/
•       Sentinel Road Safety Improvements: www.toronto.ca/services-payments/streets-parking-transportation/cycling-in-toronto/cycle-track-projects/yorkudownsview/#:~:text=In%20June%202018%2C%20Toronto%20City,and%20will%20continue%20through%202022
•       Steeles Avenue East Complete Street: www.toronto.ca/community-people/get-involved/public-consultations/infrastructure-projects/steeles-avenue-east-complete-streets/
•       The Queensway Complete Street: www.toronto.ca/community-people/get-involved/public-consultations/infrastructure-projects/the-queensway-complete-street/
•       Sheppard Avenue-Willowdale Avenue Road Resurfacing Opportunities: www.toronto.ca/community-people/get-involved/public-consultations/infrastructure-projects/sheppard-avenue-east-willowdale-avenue-east-road-safety-improvements/

In addition, City Council approved extending the pilot periods for two temporary ActiveTO Cycling Network Expansion projects on Midtown Yonge Street and Bayview Avenue East for the rest of the year when Transportation Services will report to the Infrastructure and Environment Committee and City Council on additional data, evaluation and recommendations on the future of the two temporary projects.

The ActiveTO Midtown Complete Street pilot on Yonge Street implemented cafés, cycle tracks and other streetscape elements in July 2021. The expanded CaféTO program provided urgent support to local restaurants, while the ActiveTO bikeways provided a new safe connection that mirrored the Line 1 (Yonge-University) subway line.

Community consultation has taken place, both before and during the pilot, with local businesses, four Business Improvements Areas, several neighbourhood associations and area residents. Further feedback will be gathered before making a recommendation on whether the pilot should be made permanent next year.

The ActiveTO pilot on Bayview Avenue East was implemented between Front Street East and River Street to provide a safe and direct detour to the Lower Don Trail closures. Construction of the Lower Don Trail project is expected to start this year. Extending the pilot period would allow staff to monitor the trail construction project and report back with recommendations based on findings.

The 2022 cycling infrastructure installation comes after unprecedented expansion of bikeways over the past three years in Toronto. From 2019 to 2021, including ActiveTO routes, 65 kilometres of new bikeways have been installed, as well as 47 kilometres of upgrades and enhancements to existing cycling routes.

More information is available in the Cycling Network Plan: 2022 Cycling Infrastructure Installation – First Quarter and 2021 ActiveTO Cycling Network Expansion Project Updates report: http://app.toronto.ca/tmmis/viewAgendaItemHistory.do?item=2022.IE28.7.

More information about ActiveTO is available on the City’s website:  www.toronto.ca/explore-enjoy/recreation/covid-19-activeto.

Quote:

“To be truly committed to the future of cycling in our city, we must continue to connect, grow and renew Toronto’s cycling infrastructure. As Toronto grows, it’s imperative that we offer options to get around in the city that we live, play and work in.”
– Councillor Jennifer McKelvie (Scarborough-Rouge Park), Chair of the Infrastructure and Environment Committee.

Source City of Toronto 